Past halfway point for brickwork – 700,000 brick laid – 600,000 left to go.
Waterhouse Garden really starting to take shape with most of the cavity works complete and 18 gangs of bricklayers all with plenty of work in front of them.
All QA being completed as we go with rigorous checks; this one is going to look the part when topped out.
Hats off to the site team working through a cold winter.
A little time on set-up saves hours later! From clamping pistols on top-level masonry supports, to dropping string lines 🧵 and keeping every pillar true to line — getting it right from the start is everything 💯
With the sunshine lighting up the site, it’s a proper showcase of the quality and detail the team have been delivering throughout. The brickwork is really starting to stand out now, bringing the whole development to life as we move closer to completion.
This award recognises our commitment to apprenticeships, training, and skills across Tameside — and during National Apprenticeship Week, it’s the perfect time to celebrate the people behind that commitment 🙌
Great progress continuing on site at Tariff Street. Mast climbers 13 & 14 to Block 2 have now been successfully removed, marking another key milestone.
Archie joined Kinlan Brickwork back in June 2023 on a one-week trial. Fast forward 2½ years, and he’s now officially passed his Level 2 Brickwork qualification 🧱🎓
Past halfway point for brickwork – 700,000 brick laid – 600,000 left to go.
Waterhouse Garden really starting to take shape with most of the cavity works complete and 18 gangs of bricklayers all with plenty of work in front of them.
All QA being completed as we go with rigorous checks; this one is going to look the part when topped out.
Hats off to the site team working through a cold winter.