Kinlan Brickwork Ltd have some updates on the work being carried out at Well Meadow.
9 February 2022
Progress at our site Well Meadow for our Client GRAHAM Group Showing CETCO CETBIT 300 tanking installation with CETCO termination bar. 100mm double skin block work to substation with tramlines. 140mm block work. Foamglass T4+ insulation with weak mix concrete.
Block C&D now coming to completion with the final works being completed to the hoist infill and corner details, Mast strikes now commencing to block C with D to follow.