Preparation is so important on a job that is 60% soffits and support. Pillar and detail work with the brick will be made easy if we keep to the plan.
A) get all of the ground floor blockwork complete (one less task to worry about)
B) point all soffits on the ground inside the building and store safely
C) fix angle support and soffits with great precision
A tricky detail job like this is only so if it’s not planned, fixers to get 3-5 floors complete at least then brickwork can commence on the scaffold. Watch this space.
Nights like this are a powerful reminder that progress in our industry doesn’t happen in isolation, it’s driven by collaboration, shared learning, and a genuine commitment to doing things the right way.
Cameron has just passed his Level 2 Apprenticeship with flying colours, achieving distinctions across the board, a fantastic result and a real testament to his hard work and dedication.
A little time on set-up saves hours later! From clamping pistols on top-level masonry supports, to dropping string lines and keeping every pillar true to line, getting it right from the start is everything.
With the sunshine lighting up the site, it’s a proper showcase of the quality and detail the team have been delivering throughout. The brickwork is really starting to stand out now, bringing the whole development to life as we move closer to completion.
Points Cross – United Living – Leeds
Preparation is so important on a job that is 60% soffits and support. Pillar and detail work with the brick will be made easy if we keep to the plan.
A) get all of the ground floor blockwork complete (one less task to worry about)
B) point all soffits on the ground inside the building and store safely
C) fix angle support and soffits with great precision
A tricky detail job like this is only so if it’s not planned, fixers to get 3-5 floors complete at least then brickwork can commence on the scaffold. Watch this space.
Well done team